The 158 MW Siemens (Kraftwerk Union) Steam Turbine Major was successfully overhauled and the unit was commissioned.
During Maintenance;
- Rotor Seal Replacement with Portable Lathe (HP-IP-LP)
- Diaghragms Seal Replacement with Boring Bar (HP-IP-LP),
- HP Casing First Stage Fixed Blade Replacement,
- LP Last Stage Blades Replacement,
- Spray Isolation Application has been made.
Customer |
Çelikler Holding |
Plant Name |
Tuncbilek Thermal Power Plant |
Turbine Type |
Kraftwerk Union Steam Turbine (Unit-5) |
Scope |
Turbine Major Maintenance |
Capacity |
158 MW |
Completion Date |
19.02.2022 |