10,4 MW MAN Buhar Türbini montajı Joule Energy süpervizörü gözetiminde gerçekleştirildi.
Customer |
MAN Energy Solution SE |
Plant Name |
Poltava Power Plant |
Turbine Type |
MAN Steam Turbine |
Scope |
Turbine Installation Supervision (TFA) |
Capacity |
10,4 MW |
Completion Date |
25.02.2021 |