Gaz Türbini Boroskop Muayenesi aşağıda belirtilen şekilde GT Gövdesi üzerinde belirlenmiş alanlardan ve muayene tapalarından tamamlanmıştır;
-2nd Stage Compressor Stator
-3rd Stage Compressor Stator
-6th Stage Compressor Stator
-7th Stage Compressor Stator
-8th Stage Compressor Stator
-Aft Compressor Discharge Casing
-1st Stage Nozzle Trailing Edge and 1st Stage Bucket Leading Edge
-3rd Stage Nozzle Leading Edge and 2nd Stage Bucket Trailing Edge
Müşteri |
AKSA ENERJİ |
Santral Adı |
- |
Türbin Tipi |
GE 9E Gas Turbine |
Kapsam |
Boroscope Inspection |
Kapasite |
145 MW |