Our personnel, who reached the site after cutting the coupling pins, successfully completed the following works.

-Couplings have been disassembled.
-The broken pins were disassembled.
-Leveling of damaged surfaces was carried out.
-The bearings were cleaned and greased.
-Coupling alignment measurements were taken.

Project Details

Customer

FBY Enerji  

Plant Name

FBY Enerji BES 

Turbine Type

Steam Turbine  

Scope

Repair of Coupling Pins 

Capacity

9.3 MW

FBY Enerji Biomass Plant - Replacement of Coupling Pins