Major Overhaul of 15 MW Alstom Steam Turbine at DEBA Energy facility has been completed by Joule Energy as lump sum. During the outage, the unit was commissioned after the disassembly, sandblasting, NDT, fact finding and assembly works.
Customer |
DEBA Enerji |
Plant Name |
DEBA Burak-1 Biomass Power Plant |
Scope |
Major Overhaul of Alstom Steam Turbine |
Capacity |
15 MW |
Completion Date |
17.05.2023 |