Installation of 16 MW MAN Steam Turbine was carried out under the supervision of Joule Energy supervisor.

Project Details

Customer

MAN Energy Solution SE

Plant Name

Chernomorsky Power Plant

Turbine Type

MAN Steam Turbine

Scope

Turbine Installation Supervision (TFA)

Capacity

16 MW

Completion Date

17.03.2021